THE FOLDING GATEHOW TO ERECT AND SET

DOUBLE GATE AND NOT SWING

General :

  1. Frame should be level, if not the folding gate will be difficult to open and close
  2. For achorage welding should be to rebar concrete and using dyna bolt was not recommended
  3. Anchorage should be crossing each other
  4. Bottom anchorage minimum each 60 cm
  5. Upper anchorage minimum at 3 places, depend on to the wide of folding gate

Erection Procedure:

  1. Placed the left and right pole, botom rail and then upper frame
  2. Section (A) is temporary tag weld, the place to insert the folding gate in
  3. Release section (A)
  4. Insert folding gate through section (A)
  5. Weld back section (A) after the folding gate inserted

 